Project No. 18
•  Client Name :
M/s. Delhi Metro Rail Corporation Ltd.
•  Work Detail :
Providing Collection Chamber (Khurra) and
tile work around in Median for drainage arrangement
between P-539 to P-673.
•  Date of Project:
17.12.2005
•  Letter no. :
Quot/line-3/III/Viaduct/2005
•  Tender no. :
- Do -
•  Completion Cost :
Rs.1300010.00
•  Completion Date :
30-1-06

S.no.
Descrption of Item
completed upto 15.1.2006
Work in Progress
Remarks
1.
Earth work
570 to 600
601 to 649
650 to 673
579 to 639
To be completed by 23.01.06
2
PCC work
600 to 648
648 to 673
600 to 539
To be completed by 26.01.-6.
3
Brick work in cement.
602 to 647
605 to 610
539 to 602
647 to 673
To be completed by 28.01.06
4
Plaster work.
605 to 610
610 to 637
539 to 605
637 to 673
To be completed by 30.01.06
5
NP Class RCC Pipe 150mm dia.
602 to 647
539 to 602
647 to 673
To be completed by 29.01.06.
6
Constn. of Road Gully chambers.
120 Nos.
147
To be completed by 29.01.06.